1.
Which is NOT true about the project charter:
2.
Which of the following is NOT an output of the Direct and Manage Project Work process?
3.
You have just verified that all of the work on your project is completed. Which of these things is NOT part of the Closing process?
4.
Which of the following is NOT an input to the Develop Project Management Plan process?
5.
You are a project manager starting a new project. Your manager warns you that previous projects ran into trouble. Which of the following would be BEST for you to rely on to help plan your project:
6.
You are the project manager on a construction project, and you have just received a change request. You consulted the Project Management plan, and followed the procedures laid out in the change control system. You are in the process of reviewing the change and documenting its impact. Your manager asks you why you are doing this. Which process are you doing by reviewing the change and documenting its impact?
7.
Which of the following is NOT true about the project charter?
8.
Diane is a project manager at a software company. She just got a change request from one of her stakeholders, but is concerned that it will cause a serious problem with her schedule. She called a meeting with the project team, and decided that there was a real change, and now they need to start change control. Which of the following is NOT an output of the Perform Integrated Change Control process?
9.
Which of the following is NOT true about the Project Management Plan?
10.
You are the project manager on a network engineering project. Two weeks ago, your team began executing the project. The work has been going well, and you are now a day ahead of schedule. Two stakeholders just approached you to tell you that they have an important change that needs to be made. That change will put you behind schedule. What do you do?