Question 6:
What is the primary output of the Collect Requirements process?
Explanation: The primary output of the Collect Requirements process is "Requirements Documentation," which includes the detailed project requirements.
Question 7:
What does the Project Scope Statement describe?
Explanation: The Project Scope Statement describes "the work that must be done to deliver a product, service, or result with the specified features and functions."
Question 8:
What is the purpose of the Control Scope process?
Explanation: The purpose of the Control Scope process is to "control changes to the project scope" by managing scope changes, preventing scope creep, and ensuring that the project stays on track.
Question 9:
What is the key benefit of the Validate Scope process?
Explanation: The key benefit of the Validate Scope process is that it provides a "clear understanding of project requirements and deliverables" by obtaining formal acceptance of the completed project deliverables from the stakeholders.
Question 10:
Which process involves decomposing the project deliverables and project work into smaller, more manageable components?
Explanation: The process that involves decomposing the project deliverables and project work into smaller, more manageable components is "Create WBS" (Work Breakdown Structure).