Question 21:
Which process involves managing changes to the project scope baseline?
Explanation: The process that involves managing changes to the project scope baseline is "Control Scope." It ensures that any changes to the scope are properly evaluated, approved, and implemented.
Question 22:
Which document describes how the project team will define the project scope and how the work will be validated and controlled?
Explanation: The document that describes how the project team will define the project scope and how the work will be validated and controlled is the "Scope management plan."
Question 23:
What is the primary tool used to develop the Work Breakdown Structure (WBS)?
Explanation: The primary tool used to develop the Work Breakdown Structure (WBS) is "Decomposition." It involves breaking down the project deliverables into smaller, more manageable components.
Question 24:
Which process involves formal acceptance of the completed project deliverables?
Explanation: The process that involves formal acceptance of the completed project deliverables is "Close Project or Phase." It signifies the end of the project or project phase.
Question 25:
What does Scope Creep refer to?
Explanation: Scope Creep refers to "The process of expanding the project scope without proper authorization." It often leads to project scope changes that are not evaluated and approved, resulting in project challenges.
Question 16:
Which process involves decomposing the major project deliverables into smaller, more manageable components?
Explanation: The process that involves decomposing the major project deliverables into smaller, more manageable components is "Create WBS" (Work Breakdown Structure).
Question 17:
Which document defines how project scope will be defined, validated, and controlled?
Explanation: The document that defines how project scope will be defined, validated, and controlled is the "Scope management plan." It outlines the processes and procedures to manage project scope effectively.
Question 18:
What is the primary output of the Define Scope process?
Explanation: The primary output of the Define Scope process is the "Project scope statement," which includes a detailed description of the project scope, major deliverables, assumptions, and constraints.
Question 19:
Which process involves reviewing all project deliverables to ensure that they have been completed correctly and satisfactorily?
Explanation: The process that involves reviewing all project deliverables to ensure that they have been completed correctly and satisfactorily is "Validate Scope."
Question 20:
Which technique is used to identify and document project boundaries?
Explanation: The technique used to identify and document project boundaries is "Decomposition." It involves breaking down the project into smaller components and defining their scope.