Question 11:
What is the purpose of a milestone in project scheduling?
Explanation: The purpose of a milestone in project scheduling is to "mark the completion of a significant project phase or deliverable," providing checkpoints and points of reference in the project timeline.
Question 12:
What is resource leveling in project scheduling?
Explanation: Resource leveling in project scheduling refers to "adjusting the project schedule based on resource availability" to prevent overallocation or underutilization of resources.
Question 13:
What is the purpose of a Gantt chart in project scheduling?
Explanation: The purpose of a Gantt chart in project scheduling is to "visually represent the project schedule and progress," showing the timeline of tasks, their dependencies, and their progress over time.
Question 14:
What is the critical path in project scheduling?
Explanation: The critical path in project scheduling is "the longest sequence of dependent activities that determines the project's duration," and any delay on this path will directly impact the project's overall timeline.
Question 15:
What is the purpose of schedule compression in project scheduling?
Explanation: The purpose of schedule compression in project scheduling is "to reduce the project schedule without changing the project scope," typically achieved by employing techniques such as crashing or fast-tracking.