Question 11:
What is the purpose of the Define Scope process?
Explanation: The purpose of the Define Scope process is to "define and document the project's scope" by determining a detailed description of the project and its deliverables.
Question 12:
What is the key benefit of the Control Scope process?
Explanation: The key benefit of the Control Scope process is that it "controls changes to the project scope" by monitoring scope, preventing scope creep, and ensuring that the project stays within the defined scope boundaries.
Question 13:
Which process involves reviewing project deliverables with the stakeholders to ensure that they are completed satisfactorily?
Explanation: The process that involves reviewing project deliverables with the stakeholders to ensure that they are completed satisfactorily is "Validate Scope."
Question 14:
Which technique is used to develop a detailed project scope statement?
Explanation: The technique used to develop a detailed project scope statement is "Expert judgment." Experts in the field provide their insights and knowledge to create a comprehensive scope statement.
Question 15:
Which of the following is an output of the Collect Requirements process?
Explanation: The output of the Collect Requirements process is "Requirements documentation," which includes the gathered and documented project requirements.