Question 6:
What is the purpose of a network diagram in schedule management?
Explanation: The purpose of a network diagram in schedule management is to "visually represent the project's activities and their relationships," showing the sequence and dependencies between activities.
Question 7:
What is the purpose of the Schedule Performance Index (SPI) in project scheduling?
Explanation: The purpose of the Schedule Performance Index (SPI) in project scheduling is to "measure the efficiency of the project schedule" by comparing the earned value to the planned value.
Question 8:
What is the purpose of the Schedule Network Analysis technique?
Explanation: The purpose of the Schedule Network Analysis technique is to "calculate the critical path of the project" and determine the project's duration and schedule flexibility.
Question 9:
What is crashing in project scheduling?
Explanation: Crashing in project scheduling refers to "shortening the project schedule by adding more resources" to complete activities faster and reduce the project's duration.
Question 10:
What is the purpose of the Schedule Baseline?
Explanation: The purpose of the Schedule Baseline is to "provide a snapshot of the approved project schedule" against which the actual project progress and performance are measured.