Project Schedule Management: Quiz-6 Join Now Table of Contents Check All Published QuizzesQuiz on Project Schedule ManagementMajor Take Away Project Schedule ManagementDefining the ActivitiesSequencing the Activities Estimating the Resources Required Estimating the Time Required Developing the ScheduleControlling the ScheduleCheck other Quizzes on Project Schedule ManagementCheck Published Articles on Project Schedule Management Check All Published Quizzes Attempt Now Quiz on Project Schedule Management 1. You’re managing a project to build a new project management information system. You work with the team to come up with an estimate of 27 weeks. In the best case, this could be shortened by two weeks because you can reuse a previous component. But there’s a risk that a vendor delay could cause the project to be delayed by five weeks. Use PERT to calculate a three-point estimate for this project. 28.3 weeks 27.5 weeks 25.83 weeks 26 weeks 2. What is the critical path in the activity list to the right? Start-A-B-J-Finish Start-A-B-C-Finish Start-G-H-I-J-Finish Start-A-D-E-F-Finish 3. What is the float for activity F in the activity list to the right? 0 7 8 10 4. You’re managing a construction project. You’ve decomposed work packages into activities, and your client needs a duration estimate for each activity that you come up with. Which of the following will you use for this? Milestone list Activity list Critical path analysis Project schedule network diagram 5. What’s the correct order of the Project Schedule Management planning processes? Plan Schedule Management, Define Activities, Sequence Activities, Develop Schedule, Estimate Activity Resources, Estimate Activity Durations Sequence Activities, Define Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, Develop Schedule Plan Schedule Management, Develop Schedule, Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations 6. You’re managing an interior decoration project when you find out that you need to get it done earlier than originally planned. You decide to fast-track the project. This means: Starting the project sooner and working overtime Shortening the durations of the activities and asking people to work overtime to accommodate that Assigning more people to the tasks at a greater total cost, especially for activities on the critical path Starting activities earlier and overlapping them more, which will cost more and could add risks 7. Three members of your project team want to pad their estimates because they believe there are certain risks that might materialize. What is the BEST way to handle this situation? Allow more time for the work by adding a buffer to every activity in the schedule. Tell the team members not to worry about it, and if the schedule is wrong it’s OK for the project to be late. Estimate the activities honestly, and then use a contingency reserve to cover any unexpected costs. Crash the schedule. 8. Slack is a synonym for: Lag Float Reserve Buffer 9. You’re managing a software project. You’ve created the schedule, and you need to figure out which activities cannot slip. You’ve done critical path analysis, identifying the critical path and calculating the early start and early finish for each activity. Which activities cannot slip without making the project late? The activities on the critical path The last activity in the project, because it has no float The ones with the biggest difference between ES and LF The activity with the most lag 10. Which of the following is NOT a tool or technique used in Estimate Activity Durations? Analogous estimation Three-point estimation Parametric estimation SWAG estimation Time is Up! Time's up Check All Published Quizzes Attempt Now Major Take Away Project Schedule Management Defining the ActivitiesSequencing the Activities Estimating the Resources Required Estimating the Time Required Developing the ScheduleControlling the Schedule Check other Quizzes on Project Schedule Management Project Schedule Management: Quiz-7 Attempt Now Project Schedule Management: Quiz-6 Attempt Now Project Schedule Management: Quiz-5 Attempt Now Project Schedule Management: Quiz-4 Attempt Now Project Schedule Management: Quiz-3 Attempt Now Project Schedule Management: Quiz-2 Attempt Now Project Schedule Management: Quiz-1 Attempt Now Check Published Articles on Project Schedule Management Creating an Effective Schedule Baseline for Project Management Attempt Now Maximizing Efficiency: A Guide to Control Schedule Process in Project Management Attempt Now Project Management Best Practices: Develop Schedule Process Attempt Now The Role of Activity Duration Estimation in Successful Project Scheduling Attempt Now Mastering the Art of Sequence Activities in Project Schedule Management Attempt Now Define Activities in Project Schedule Management: A Step-by-Step Guide Attempt Now Plan Schedule Management Process; Importance, Steps, Tools & Techniques, Inputs & Outputs Attempt Now What is Project Schedule Management Plan? Attempt Now All About Project Management Institute (PMI) & PMI Certifications, Importance & Benefits Attempt Now What are PDUs, Requirements, Various Categories, Earning PDUs Attempt Now All About PMP certification. Eligibility & Work Experience required Attempt Now TOP 5 Process Groups of Project Management Attempt Now All about 10 Knowledge Areas of PMBOK (With 100+ Quizzes) Attempt Now Read more articles Previous PostProject Schedule Management: Quiz-5 Next PostProject Schedule Management: Quiz-7 You Might Also Like Practice PMP Questions: Quiz-10 January 5, 2023 Practice PMP Questions: Quiz-18 January 6, 2023 Introduction to Project Management: Quiz-11 January 6, 2023 Project Resource Management: Quiz-7 January 2, 2023 Project Integration Management: Quiz-2 December 31, 2022 Practice PMP Questions: Quiz-4 January 5, 2023 Project Cost Management: Quiz-1 December 31, 2022 Project Schedule Management: Quiz-3 December 31, 2022 Project Cost Management: Quiz-6 January 7, 2023 Project Cost Management: Quiz-9 January 7, 2023 Share my adventures Share this content Opens in a new window Twitter Opens in a new window Facebook Opens in a new window Pinterest Opens in a new window LinkedIn Opens in a new window Viber Opens in a new window VK Opens in a new window Reddit Opens in a new window Tumblr Opens in a new window Viadeo Opens in a new window WhatsApp