1.
As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except:
2.
You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response?
3.
You are a project manager for a telecommunications firm. You’re working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response?
4.
You are a project manager and are in the Closing processes of the project. Your customer has been presented with a formal acceptance and sign-off document. They refuse to sign, claiming the product does not meet their expectations. You know that this situation could have been prevented by doing all of the following except:
5.
As a project manager, you’re responsible for maintaining and ensuring integrity for all of the following except:
6.
You are a project manager for a manufacturing firm that produces Civil War–era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem?
7.
You are a project manager for a telecommunications firm. You’re working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors invites you to lunch. What is the most appropriate response?
8.
Integrity in the project management field is accomplished through all of the following except:
9.
As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following:
10.
You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do?