1.
All of the following are characteristics of the project Closing processes except:
2.
According to the Guide to the PMBOK, the project manager is identified and assigned during which process?
3.
All of the following are true regarding the ADM method except:
4.
What type of organization experiences the least amount of stress during project closeout?
5.
You work for a company that writes billing software programs for the communication industry. You’ve just been assigned a new project. The customer is located in a distant country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You might do which of the following given these circumstances?
6.
Which of the following are tools and techniques of the Initiation process?
7.
Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should:
8.
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC?
9.
You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true?
10.
You have been assigned to a project that will allow job seekers to fill out applications and submit them via the company website. You report to the VP of human resources. You are also responsible for screening applications for the information technology division and setting up interviews. The project coordinator has asked for the latest version of your changes to the online application page for his review. Which organizational structure do you work in?