1.
You’re planning an IT project to set up a development environment, including designing and building a computer room, installing the operating systems and software, and performing a security evaluation. Your project includes three different activities that involve three different network technicians splicing ends onto wires in order to build their own ethernet cables, because that’s less expensive than buying prepackaged ones. Every ethernet cable must be tested with a qualification tester. That’s an expensive piece of equipment, and there are only a few of them that must be shared among all of the technicians in the company. You need to plan your schedule based on the availability of the testing equipment. What’s the best place to find that information?
2.
A software project team lead is working with stakeholders to make sure that there’s formal, documented acceptance of every one of the project deliverables. Which of the following best describes the work that she’s doing?
3.
You’re managing an architecture project to design an extension on an existing building. One of the stakeholders has been adamant that the plans should not include an interior supporting wall, because she wants to be able to reconfigure the floorplan. Where do you document this information?
4.
You’re in the process of working with the project stakeholders, figuring out what they need, and writing it down. Which of the following is a tool or technique that you would use?
5.
The CFO of a company tells you that you need to include a new feature in software that’s being produced by a project you are managing. The deadline for the project is tight, and if you take on the extra work then the project will come in late. What best describes the first thing that you should do?
6.
You’re working on an IT project to set up a development environment, including designing and building a computer room, installing the operating systems and software, and performing a security evaluation. You need at least two weeks to order the hardware before you can configure it and install the operating systems. Which of the following best describes this relationship?
7.
A project manager is analyzing deliverables and subdividing them into smaller, more manageable components. This project manager is performing which process?
8.
Which of the following best describes the role of the project sponsor?
9.
Which of the following is not a part of the Project Management plan?
10.
You’re managing a project for a military subcontractor to modify the software for a missile guidance system. You’re planning the project, and need to take into account information about the company’s operating environment. Which of the following is not an example of the factors you are looking at?