1.
You are the manager of a research group that is developing a new chemical material. You hire a person from a competing company who has a great deal of expertise in this area. The person contributes greatly to the progress of your project. During conversations with the person you determine that many of this person’s ideas were developed by the competing company. What do you do?
2.
You are the project manager for a project that has high visibility. Your manager wants you to prepare a presentation for him to present at a conference. Most of the material in the presentation will be facts that are the results of your project. Your manager intends to present the material under his own name. Your name will not appear. What should you do?
3.
You are the project manager for a large project that is completed on time and on budget. The customer and all of the stakeholders are pleased with the results. As a direct result of the successful completion of the project, your manager approves a bonus of $25,000 to you. There are fifteen members of the project team. One of the people on the project team has been a very low contributor to the project; the other fourteen have all been above standard. What should you do with the money?
4.
You are managing a project in a foreign country. In this country there is a normal practice for business people to exchange gifts when very large contracts, such as the one you are working on, are signed. The gift is of a greater value than your company’s policy for gift exchange will allow. You have given a gift of similar value to the customer’s representative already. What should you do?
5.
You are managing a project and the customer’s engineers visit your facility on an inspection and general getting acquainted tour. During the tour they make the comment that the parts that are being designed should be in stainless steel instead of plain steel with enamel. What should you do?
6.
Which of the following is an example of a conflict of interest?
7.
You are the project manager for a high visibility project. The margin on this project is low, and it is extremely important that the cost estimates for the work on the project be accurate. While reviewing the cost estimates for this project you notice that one of the cost estimates for an element in the WBS is 10% higher than two previous projects for very similar work. What should you do?
8.
You are the project manager for a large project. Some members of the project team have come to you and asked that they be permitted to work on a flexible schedule. Some of the other team members feel that it is important that all team members be on site at all times unless they are absent for business reasons. What should you do?
9.
You are managing a project that is in process. A large and unexpected problem occurs that will cause a delay in the schedule in excess of the contingency schedule for the project. What should you do?
10.
One of the members of your project team comes to you and says that he heard that one of the suppliers to the project had given a substantial gift to one of the project team members in hopes that the team member would favor his company with a purchase order. The company was favored with a purchase order for the parts. What should you do?
11.
You are a project manager working on a project to market a new product. The deliverables of the project have been established, and the project work has begun. A contract to deliver the deliverables has been signed. The customer who has signed the contract has telephoned you to request additional work to be done on the project. This work will affect the budget but not the schedule of the project. This project has a high priority with your company. What should you do next?