1.
You are initiating a project that has a virtual team. Half of your team members will be located in another country, where they are working for a subcontractor. The subcontractor’s team members speak a different language than your team does. When you need to get information to them, it must first be translated. This is an example of:
2.
You are reviewing performance goals to figure out how much bonus to pay your team members. What document would you consult to find your team’s bonus plan?
3.
Which of the following is not a tool or technique of Perform Qualitative Risk Analysis?
4.
Your top team member has performed extremely well, and you want to reward her. She knows that you don’t have enough money in the budget to give her a bonus, so she approaches you and requests an extra day off, even though she is out of vacation days. She asks if she can take one of her sick days, even though the company doesn’t allow that. Which of the following is correct?
5.
Complete the following sentence: “The later a defect is found, __________ .”
6.
Your project team has completed the project work. All of the following must be done before the project can be closed except:
7.
You are managing a software engineering project when two team members come to you with a conflict. The lead developer has identified an important project risk: you have a subcontractor that may not deliver on time. The team estimates that there is a 40% chance that the subcontractor will fail to deliver. If that happens, it will cost an additional $15,250 to pay your engineers to rewrite the work, and the delay will cost the company $20,000 in lost business. Another team member points out an opportunity to save money an another area to offset the risk: if an existing component can be adapted, it will save the project $4,500 in engineering costs. There is a 65% probability that the team can take advantage of that opportunity. What is the expected monetary value (EMV) of these two things?
8.
While creating a project charter, you discover a new project management software tool has come onto the market. You spend the weekend taking an online tutorial to learn about it. This is an example of:
9.
Joe is a project manager on an industrial design project. He has found a pattern of defects occurring in all of his projects over the past few years, and he thinks there might be a problem in the process his company is using that is causing it. He uses Ishikawa diagrams to come up with the root cause for this trend over projects so that he can make recommendations for process changes to avoid this problem in the future. What process is he performing?
10.
During procurement closure, a procurement audit includes all of the following except: