1.
You’re managing a software project when your customer informs you that a schedule change is necessary. Which is the BEST thing to do?
2.
For that same network diagram below, what’s the float for activity A?
3.
You’re managing a construction project. You’ve decomposed work packages into activities, and your client needs a duration estimate for each activity that you came up with. Which of the following BEST describes what you are doing?
4.
Your company has previously run other projects similar to the one you’re currently managing. What is the BEST way to use that information?
5.
Given the network diagram below, what’s the critical path?
6.
You’re planning the schedule for a highway construction project, but the final date you came up with will run into the next budget year. The state comes up with capital from a reserve fund, and now you can increase the budget for your resources. What’s the BEST way to compress the schedule?
7.
For that same network diagram below, what’s the float for activity E?