1.
A project manager works in a company favoring the weakest authority for the project manager. The type of organization that holds the project manager to be the weakest is:
2.
In a very large project having a budget of $5 million and a project team of over one hundred persons, the project manager constructs a work breakdown structure. The project manager will do the WBS to the detail level of which of the following?
3.
The coordinated undertaking of interrelated activities directed toward a specific goal that has a finite period of performance is a:
5.
A project manager has been asked by the client to meet the promise date of the project. The project manager analyzes the schedule before promising a date to the customer. The project manager uses the program evaluation and review technique to evaluate the project schedule. She decides that based on the results of the PERT calculations she can promise a delivery date of June 30. The expected value of the project completion date is May 30. If the project manager is willing to accept a 5% probability that the project will be delivered later than June 30, what is the standard deviation of the durations of the activities on the critical path? Assume a five day work week.
6.
The document that is proof of upper management’s commitment to the project and gives the authority to manage the project to the project manager is called:
7.
A project is proposed to a customer. Price and schedule for delivery are agreed upon. The work breakdown structure is agreed to as well. The customer requests that one of the milestones of the project be completed by a certain date. The project schedule is reviewed, and it is found that the expected completion date for this milestone is considerably earlier than the date requested by the customer. The date for this milestone is which of the following?
8.
A project manager is managing a project. The original scope baseline of the project was budgeted at $100,000. Since work on the project started there have been seventeen authorized and approved changes to the project. The changes have a value of $17,000 and the cost of investigating them prior to their approval was $2,500. What is the current budget for the project?
9.
During the life of a project, the project will go through several phases— initiating, planning, execution, and closeout. Which phase of the project is likely to have the greatest amount of its funding spent?
10.
During the course of the project it is important that the stakeholders be informed of the progress of the project. One of the reports that is frequently used is a progress report. Which of the following is true about progress reports?